Your ADU application was marked incomplete. What now?
An incomplete notice feels like a rejection. It isn't one. It is a list, and since 2026 the city is held to that list.
- By the Lotline Editorial Team
- Reviewed
- 3 min read
- Sources
At a glance
Key points
What the notice has to contain
A bare "application incomplete" isn't enough. The permitting agency must give you a list of the incomplete items together with a description of how the application can be made complete, and it must do so with its written notice.1
The list is the list
This is the part that changed how resubmittals work. When the agency reviews what you send back, it cannot require an item that was not included in its incomplete list.1 Its job on the second pass is to decide whether you have remedied the listed items.
Two limits are worth understanding:
- The rule concerns completeness. Whether the design complies with setbacks, height or the building code is decided afterwards, in the 60-day approval period, and a complete application can still be denied.
- The rule protects you only for what you actually changed. If your resubmittal alters the design, expect the changed sheets to be looked at afresh.
How to answer it
A response is easier to review when it follows the city's list item by item. A format that works:
- Number your response to match theirs. Item 1 in the notice is item 1 in your reply.
- Say where the fix is. Give the sheet number and detail, such as "Sheet A-1, setback dimension added at north property line".
- Change only what was asked for, and cloud or highlight the revisions on the drawings.
- Attach the notice itself to your resubmittal so the list travels with the file.
- Keep proof of the date you resubmitted. A new 15-business-day completeness review runs from it.1
If the city doesn't answer within that period, the resubmitted application is deemed complete.1
When an item looks wrong
Sometimes a listed item asks for something you believe the city can't require. State law says that only an ADU ordinance consistent with the state rules can be the basis for delaying or denying the permit.1
You have two routes, and they aren't exclusive. You can supply the item and move on, which is often quicker. Or you can use the appeal that the law requires every agency to offer for incomplete determinations.1 The agency then has 60 business days to give a final written answer.1 Weigh that period against the cost of simply complying; for a small item, the appeal can take longer than the fix.
Incomplete is not denied
The two outcomes are different and so are the documents. A denial must come with a full set of written comments listing what is defective or deficient and how to remedy it.1 If what you received reads like design objections under an "incomplete" heading, it is reasonable to ask the department which of the two it has issued.
Common questions
Can the city add new items after I resubmit?
How long does the city have to review my resubmittal?
Is there a deadline for appealing an incomplete notice?
Keep reading
About this page
- Written by
- The Lotline Editorial Team. Editorial policy
- Where it comes from
- We wrote this from material published by California Legislative Information and City of Menlo Park and Los Angeles County Department of Regional Planning. You'll find each document, and the part we used, under References below.
- How it was checked
- Before publishing, we checked each statement against the original wording of its source. How we work
- Last reviewed
- . Rules and city procedures change, so confirm current requirements with your permitting agency.
- Corrections
- Email support@lotlinepermits.com. We check every report against the document and fix what is wrong.
References
- 1California Government Code, Title 7, Division 1, Chapter 13, Article 2 (Sections 66314 to 66331)California Legislative Information. Read on November 10, 2026.Cited: § 66317(a)(2)(B); § 66317(a)(2)(D); § 66317(d)(1); § 66317(a)(2)(E); § 66317(d)(2); § 66317(a)(2)(F); § 66317(c); § 66317(b).
- 2Accessory Dwelling Unit (ADU) Application ChecklistCity of Menlo Park, Community Development, Planning Division. Dated March 19, 2026. Read on November 10, 2026.Cited: page 1, General Information.
- 3Accessory Dwelling Units: Senate Bill 543 and Assembly Bill 1154 (memo to staff)Los Angeles County Department of Regional Planning. Dated December 30, 2025. Read on November 10, 2026.Cited: page 1.
General information, not legal advice. Read the disclaimer.