City notesSacramento County, California
Getting an ADU permit in Sacramento
Sacramento runs ADUs through Planning before Building, allows two per lot, and prints its fee and sprinkler thresholds on a two-page handout. One of those thresholds is worded differently from the statute.
- By the Lotline Editorial Team
- Reviewed
- 2 min read
- Sources
At a glance
Key points
State rule and Sacramento practice, side by side
Where the two say the same thing, and where they differ.
Impact fee threshold
California statute
No impact fee may be charged on an ADU with 750 square feet of interior livable space or less, or on a junior ADU with 500 square feet or less.2
Sacramento
The handout says impact fees are waived for ADUs of less than 750 square feet and applied to ADUs of 750 square feet and greater.1
The statute protects a unit of 750 square feet or less. The handout's wording, less than 750, would leave a unit of exactly 750 on the other side of the line. If your plan is at 750, raise it with the Building Division before fees are calculated.
Fire sprinklers
California statute
An ADU does not need fire sprinklers if they are not required for the primary residence.3
Sacramento
A detached ADU is exempt from sprinklers if the main home is not sprinklered and the ADU, not counting a garage, is no larger than 1,200 square feet.1
Attached ADU size
California statute
A local maximum size cannot be set below 850 square feet of interior livable space, or 1,000 square feet for an ADU with more than one bedroom.3
Sacramento
An attached ADU may be 50% of the primary structure or 850 square feet, whichever is greater, rising to 1,000 square feet with two or more bedrooms.1
About the handout
The city's Building Division summarizes its ADU requirements in handout CDD-0423. Page one is marked as revised on January 29, 2026.1 Page two still shows a 2022 revision date1, and the city calls the handout a live document.1 Fees, sprinklers and water service are all on page two, so confirm those points with the Building Division.
Planning before Building
You can't go straight to a building permit. Planning approval, or an approval for concurrent review, has to be in hand first.1 Concurrent review is requested on a Memorandum of Understanding form and needs sign-off from senior Planning staff.1
If an existing structure is coming down to make room, the wrecking permit approval comes before that.1
How many and how large
Sacramento allows two ADUs on a lot, attached or detached.1 Detached units share one allowance: their combined floor area can't exceed 1,200 square feet.1 An attached ADU may be half the size of the primary structure or 850 square feet, whichever is greater, or 1,000 square feet with two or more bedrooms.1
Submitting plans
Electronic plan check is available, and paper submittal at the public counter is still accepted.1 A complete set includes structural plans, an electrical layout, Energy Code and CalGreen compliance documents, and photovoltaic solar plans.1
Each attached and detached ADU needs its own address, requested at submittal.1 There is an unusual extra for alley units: if the alley has no alley or street sign, the applicant is responsible for installing one.1
Sprinklers
The handout gives two exemptions:
- Detached: the main home isn't sprinklered and the ADU, not counting a garage, is no more than 1,200 square feet.1
- Attached: the home isn't sprinklered, the addition is no more than half the original structure, and the whole building stays within 3,600 square feet.1
Water and power
City code allows one water service connection per lot, so an ADU doesn't need its own water meter tap.1 For solar, the handout directs applicants to SMUD for panel location, utility changes, timelines and cost.1
Fees
The handout states that impact fees are waived for ADUs of less than 750 square feet and applied at 750 and above.1 School district impact fees apply and are dealt with directly with the district.1
If you want numbers before committing, the Building Division will prepare a permit fee estimate for a $164 estimating fee.1
Our read
Sequence is the thing to get right in Sacramento: Planning, then Building, with concurrent review as the way to overlap them. On a design near 750 square feet, settle the fee question in writing early.
Common questions
How many ADUs can I build on one lot in Sacramento?
Does an ADU in Sacramento need its own water meter?
Can I apply for a building permit before Planning approves the ADU?
Keep reading
About this page
- Written by
- The Lotline Editorial Team. Editorial policy
- Where it comes from
- We wrote this from material published by City of Sacramento and California Legislative Information. You'll find each document, and the part we used, under References below.
- How it was checked
- Before publishing, we checked each statement against the original wording of its source. How we work
- Last reviewed
- . Rules and city procedures change, so confirm current requirements with your permitting agency.
- Corrections
- Email support@lotlinepermits.com. We check every report against the document and fix what is wrong.
References
- 1CDD-0423: Accessory Dwelling Units (ADU) handoutCity of Sacramento, Community Development Department. Dated January 29, 2026. Read on November 10, 2026.Cited: page 1, Building Division Submittal Requirements; page 1, How Many Can I Build?; page 2, Water Service Requirements; page 2, Building Permit Fees and Impact Fees; page 2, Fire Sprinkler Requirements; page 1, Maximum Size; page 1, footer; page 2, footer; page 2, Additional Notes; pages 1-2; page 2, Addressing Requirements; page 2, Photovoltaic (PV) Requirements.
- 2California Government Code, Title 7, Division 1, Chapter 13, Article 1 (Sections 66310 to 66313.5)California Legislative Information. Read on November 10, 2026.Cited: § 66311.5(c)(1).
- 3California Government Code, Title 7, Division 1, Chapter 13, Article 2 (Sections 66314 to 66331)California Legislative Information. Read on November 10, 2026.Cited: § 66314(d)(12); § 66321(b)(2).
General information, not legal advice. Read the disclaimer.