City notesLos Angeles County, California
Converting a garage to an ADU in Long Beach
Long Beach publishes a fill-in application for simple garage conversions, and a separate route through pre-approved plans. Which one you can use depends on your zone, your garage and where the property sits.
- By the Lotline Editorial Team
- Reviewed
- 4 min read
- Sources
At a glance
Key points
- The city's garage conversion application is limited to the existing footprint of a single-story garage.1
- Coastal zone and historic district properties can't use it.1
- Fire separation can require more distance than the zoning setback.2
- A conversion that follows the city's prescriptive bulletin doesn't need plans signed by an architect or engineer.2
State rule and Long Beach practice, side by side
Where the two say the same thing, and where they differ.
Side and rear setback
California statute
For a new ADU that is not a conversion, the side and rear setback a city requires can be no more than four feet.3
Long Beach
An ADU's location has to meet whichever is stricter - the zoning setback or the Building Code fire separation distance.2
The four-foot figure is a zoning limit. Long Beach's building staff apply the fire separation distance on top of it, and the city's own example ends at five feet.
Converted structures
California statute
No setback can be required for an existing living area or accessory structure converted to an ADU.3
Long Beach
The city's garage conversion application only covers conversions within the existing floor area of a single-story garage, with no added floor area or footprint.1
Can you use the city's conversion application?
Long Beach's Building and Safety Bureau has an "Accessory Dwelling Unit Garage Conversion Application" that lets an owner draw the site plan and floor plan on the form's own pages. It's the simplest route, and it is narrow. To qualify, the project must:
- be created solely from the existing floor area of a single-story garage in a single-family zone, with no added floor area or footprint1
- not be in the coastal zone or a historic district1
- not be in zones R-M, R-4-M, RP or PUD1
- have utility sizes that are adequate for the ADU and verified before the permit is issued1
There's also a paperwork step that surprises people. You submit your grant deed, city staff prepare a covenant, and that covenant has to be recorded before the permit is issued.1
If your garage fails any of these tests, you aren't barred from converting it. You are on the standard plan review route, which needs a complete set of construction documents including an energy report.2
What the drawings have to show
Some of the items on the application's site plan and floor plan lists are easy to miss:
- the distance to the nearest public fire hydrant1
- any electrical subpanel, with justification that the existing panel can carry it1
- U-factor and SHGC values for the windows1
Do you need an architect or engineer?
Not always. The Bureau's FAQ says plans signed by a registered design professional are not required for a garage conversion where the work fully complies with IB-010, the city's bulletin on prescriptive wood-frame construction.2 Step outside those prescriptive provisions and you will need one.
Setbacks: the building code can ask for more
This is the Long Beach point most likely to affect a new detached ADU. Planning staff apply zoning setbacks; building staff apply fire separation distances; and the ADU has to meet whichever is more restrictive.2 Fire separation runs from 0 to 5 feet depending on wall construction, openings and sprinklers.2 The city's example is a four-foot zoning setback against a five-foot fire separation, where the ADU ends up five feet from the property line.2
The distance between the ADU and the main house is worked out the same way, by adding together the separation each building needs.2 On a tight lot, wall rating and window placement on the facing sides can decide whether a design fits.
Submitting
The FAQ describes in-person submittal at the Permit Center with fees paid the same day2, documents as PDF files on a USB device2, and appointments recommended.2 The conversion application goes further and says an appointment must be made.1 The FAQ was last revised in August 20242, and the conversion application carries no single revision date, with one of its attached forms dated August 2021.1 Both predate the 2026 state changes, so confirm the current submittal method with the Permit Center before you go.
With one existing single-family home on the lot, a single set of documents and one combination building permit application covers the building, electrical, mechanical and plumbing work.2 Ask for the ADU's address at the same time using form APP-015.2
A property owner, a California-licensed contractor or an authorized agent can pull the permit.2
Utilities and sprinklers
You have to decide whether the ADU will share the main house's utility services or have its own meters, because different requirements can follow from that choice.2
A garage conversion needs fire sprinklers only where the existing house has them or is required to.2 If they are needed, the sprinkler work has its own fire application, plan review and permit.2
The pre-approved plan route
Long Beach calls its pre-approved designs PAADUs. They are for new units on single-family zoned properties.2 The plans belong to the design professionals who drew them and are available only from those professionals.2 In return for accepting the design largely as drawn2, the project is eligible for over-the-counter minor plan review.2
Our read
Check eligibility for the conversion application first; the coastal zone, historic district and zone exclusions decide it before any drawing does. If you qualify, the two items most likely to slow you down are the covenant and the electrical panel. If you are building new, design the walls facing the property line and the main house around fire separation from the start.
Common questions
Do I need an architect for a garage conversion in Long Beach?
Do I have to replace the parking I lose?
Does a garage conversion need fire sprinklers?
Keep reading
About this page
- Written by
- The Lotline Editorial Team. Editorial policy
- Where it comes from
- We wrote this from material published by City of Long Beach and California Legislative Information. You'll find each document, and the part we used, under References below.
- How it was checked
- Before publishing, we checked each statement against the original wording of its source. How we work
- Last reviewed
- . Rules and city procedures change, so confirm current requirements with your permitting agency.
- Corrections
- Email support@lotlinepermits.com. We check every report against the document and fix what is wrong.
References
- 1Accessory Dwelling Unit Garage Conversion ApplicationCity of Long Beach, Community Development Department, Building and Safety Bureau. Read on November 10, 2026.Cited: page 2, item 1; page 2, item 3; page 2, item 6; page 2, item 5; page 2, item 4; page 3, Site Plan Instructions; page 3, Floor Plan Instructions; page 2, Instructions; attached sewer fee form.
- 2FAQ-001: Accessory Dwelling Units and Two-Unit Residential Developments (SB 9)City of Long Beach, Community Development Department, Building and Safety Bureau. Dated August 21, 2024. Read on November 10, 2026.Cited: pages 1-2, Q2; page 4, Q9; page 7, Q22; page 1, Q1; page 2, Q2; page 4, Q8; page 2, Q3; page 3, Q6; page 1, header; page 3, Q7; pages 7-8, Q26; page 8, Q28; page 3, Q5; page 7, Q25; page 5, Q13; page 5, Q10; page 5, Q12; page 5, Q11.
- 3California Government Code, Title 7, Division 1, Chapter 13, Article 2 (Sections 66314 to 66331)California Legislative Information. Read on November 10, 2026.Cited: § 66314(d)(7); § 66314(d)(12); § 66314(d)(11).
General information, not legal advice. Read the disclaimer.